Top SAP C_TSCM42_67 Courses Online - Updated [Dec-2021]
C_TSCM42_67 Practice Dumps - Verified By Pass4sureCert Updated 108 Questions
SAP C_TSCM42_67 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Material and Capacity Requirements Planning > 12% | Characterize production-relevant planning functionality. |
| Production Orders Basics (PP-SFC) 8% - 12% | Apply production order functionality. |
| Material Requirements Planning (PP-MRP) > 12% | Explore material requirements planning functions. |
| Master Data (LDM) 8% - 12% | Set up master data for production planning and manufacturing. |
| Application Overview and Background < 8% | Characterize the interplay of master data, planning, ATP, and production functionality. |
| Process Orders (PP-PI) < 8% | Identify specific properties of process orders. |
| Lean Manufacturing (PP-REM, PP-KAB) 8% - 12% | Outline the highlights of repetitive manufacturing and kanban. |
| Basics on SAP Business Processes (E-Learnings) < 8% | Outline the scope of SAP SCM business processes. |
| Production Orders Advanced (PP-SFC) > 12% | Configure production order functionality. |
NEW QUESTION 26
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for scheduling? (Choose three.)
- A. General values from work scheduling view in the material master
- B. User-defined field from operation in task list
- C. General operation values in task list
- D. General item values in bill of materials
- E. Standard value from operation in task list
Answer: B,C,E
NEW QUESTION 27
Which function is supported by production orders?
- A. Automatic selection of a work center at order release
- B. Automatic reading of PP master data at order release
- C. Automatic creation of transfer orders at order release
- D. Automatic printing of order documents at order creation
Answer: C
NEW QUESTION 28
Which of the following functions are available in SAP ECC when using capacity leveling? (Choose three)
- A. Lot size optimization
- B. Midpoint scheduling
- C. Setup time reduction
- D. Batch size optimization
- E. Finite capacity scheduling
Answer: B,C,E
NEW QUESTION 29
Which of the following master data is necessary for the creation of material reservations for production orders?
- A. Production/resource tools
- B. Routings
- C. Material master records
- D. Production versions
Answer: C
NEW QUESTION 30
In what sequence are the steps of material requirements planning performed in SAP ECC?
- A. 1. Net requirements calculation
2. Lot sizing
3. Scheduling
4. Determination of the procurement type - B. 1. Net requirements calculation
2. Lot sizing
3. Determination of the procurement type
4. Scheduling - C. 1. Calculation of safety stock
2. Lot sizing
3. Scheduling
4. Determination of the procurement type - D. 1. Availability check
2. Lot sizing
3. Determination of the procurement type
4. Scheduling
Answer: B
NEW QUESTION 31
What is SAP Solution Manager?
- A. A standalone system that communicates with other systems in a system landscape
- B. An add-on industry solution
- C. A managed system in a system landscape
- D. A transaction in the SAP ECC system
Answer: A
NEW QUESTION 32
Which functions can be triggered before releasing a production order? (Choose three)
- A. Confirmation
- B. Selection of a BOM
- C. Selection of a routing
- D. Stock determination
- E. Scheduling
Answer: B,C,E
NEW QUESTION 33
During the processing of production orders planned and actual costs are determined.
On which of the following objects can you collect these costs? (Choose two)
- A. Planned order
- B. Product cost collector
- C. Work center
- D. Production order
Answer: B,D
NEW QUESTION 34
What is a feature of the simu-lation mode for material requirements planning in SAP ECC?
- A. It posts planning results to the database automatically.
- B. It triggers multilevel bottom-up scheduling.
- C. It propagates exception messages from a component to the finished product.
- D. It calculates the delay time which may occur in planning.
Answer: D
NEW QUESTION 35
Which statements are true for ECC Long-Term Planning (LTP)? (Choose two.)
- A. In case of external procurement, long-term planning creates purchase requisitions.
- B. A planning scenario must be released to use it in long-term planning.
- C. Long-term planning generally is operational planning of important components.
- D. Reorder point planned materials can be included in long-term planning.
Answer: B,D
NEW QUESTION 36
Which of the following functions does SAP Supply Chain Management (SCM) offer?
- A. Product development, safety, quality, and maintenance
- B. Communication with customers through different interaction channels
- C. Planning of supply chains across company boundaries
- D. Optimization of the procurement strategy with the supplier pool
Answer: C
NEW QUESTION 37
You want to use the different options for planning in SAP ECC.
What is the correct sequence of the planning procedures?
- A. Sales and operations planning -> Demand management -> Long-term planning -> Material requirements planning -> Capacity planning
- B. Demand management -> Sales and operations planning -> Capacity planning -> Long-term planning -> Material requirements planning
- C. Material requirements planning -> Demand management -> Sales and operations planning -> Long-term planning -> Capacity planning
- D. Long-term planning -> Sales and operations planning -> Demand management -> Material requirements planning -> Capacity planning
Answer: A
NEW QUESTION 38
Which of the following situations occur when a production order is set to Technically Complete (TECO)?
(Choose three.)
- A. Purchase orders for external operations or non-stock materials are deleted.
- B. Reservations are deleted.
- C. The order is no longer relevant for Material Requirements Planning.
- D. The order and its operations receive the system status Locked (LKD).
- E. Capacity requirements are deleted.
Answer: B,C,E
NEW QUESTION 39
Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?
- A. Set "Container full"
- B. Set "Container empty"
- C. Set "Container in process"
- D. Set "Container in transport"
Answer: A
NEW QUESTION 40
You want to use the function "Read PP master data" in the production order.
However, while calling the function you receive an error message.
What could be the reason?
- A. Goods movements have been posted.
- B. Order papers have been printed.
- C. The material availability check has been performed.
- D. The production order has been released.
Answer: A
NEW QUESTION 41
What do you have to consider regarding lot size procedures?
- A. If a long-term lot size is used, procurement is conducted with a long-term perspective.
- B. The procurement quantity of a lot size procedure can be specified using a safety time period profile.
- C. If a make-to-order production strategy is used, only the lot-for-lot (exact) lot size can be applied.
- D. The lot size quantity can be influenced using a minimum lot size and the rounding profile.
Answer: D
NEW QUESTION 42
Which of the following statements about the planning functions available in SAP ECC is correct?
- A. Material requirements planning (MRP) includes automatic capacity leveling.
- B. Long-term planning (LTP) is a long-term form of forecast planning.
- C. Master production scheduling (MPS) refers to preferred planning of important materials.
- D. In demand management (DM) material shortage situations are identified and corresponding receipt elements are created.
Answer: C
NEW QUESTION 43
The availability check during production order creation should use a different scope of check than during order release.
How can you fulfill this requirement?
- A. Maintain appropriate availability checking rules in the order type-dependent parameters.
- B. Maintain appropriate availability checking rules in the production scheduling profile.
- C. Maintain appropriate checking rules in checking control for order creation and order release.
- D. Maintain an appropriate availability checking group in the material master.
Answer: C
NEW QUESTION 44
What do you have to consider regarding consumption? (Choose two)
- A. Consumption is restructured with the planning run.
- B. Consumption takes place on the material level between the planned independent requirements and the planned orders.
- C. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
- D. Consumption can take place between order reservations and planned independent requirements, depending on the strategy.
Answer: C,D
NEW QUESTION 45
Which Customizing element controls the determination of planned costs in production orders?
- A. Settlement profile
- B. Costing variant
- C. Accounting type
- D. Calculation procedure
Answer: B
NEW QUESTION 46
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
- A. Total planning online
- B. Multi-level single-item planning with the "simulation mode" option
- C. Multi-level single-item planning with the "display material list" option
- D. Interactive single-item planning for the delayed assembly
Answer: B
NEW QUESTION 47
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)
- A. Availability check
- B. Resource selection
- C. Digital signature
- D. Electronic batch record
- E. Approved master recipes
Answer: C,D,E
NEW QUESTION 48
Which options can you offer someone who uses the SAP ECC system for production orders and requires support for material supply in production? (Choose three.)
- A. Logistics Information System (LIS)
- B. Pick list
- C. Material directory
- D. Pull list
- E. Automatic generation of a transport order
Answer: B,D,E
NEW QUESTION 49
What do you have to consider, when you use the ATP (Available To Promise) checks for material? (Choose two)
- A. ATP checks can be adjusted to also consider future requirements and receipts.
- B. ATP checks are automatically performed during Material Requirements Planning (MRP) runs.
- C. ATP checks are mandatory for lead-time scheduling.
- D. ATP checks can be carried out automatically when releasing a production order.
- E. ATP checks are used to evaluate the free capacity on a certain work center.
Answer: A,D
NEW QUESTION 50
In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.
What does a firming type define? (Choose two)
- A. Handling existing procurement proposals outside the planning time fence.
- B. Handling existing procurement proposals within a planning time fence.
- C. Handling new procurement proposals that need to be created due to new requirements within the planning time fence.
- D. Handling new requirements within the planning time fence.
Answer: B,C
NEW QUESTION 51
......